| Activity | 2004 | 2005 | ||||||||||||||||
| May | June | July | August | September | October | November | December | January | February | March | April | May | June | July | August | September | October | |
| Stock Condition Survey - complete | ||||||||||||||||||
| Public Consultation on Plans | ||||||||||||||||||
| Review of plans by ESG & approval | ||||||||||||||||||
| Initial Cost Plan produced | ||||||||||||||||||
| Draft Business Plan produced | ||||||||||||||||||
| Draft Business Plan approved by LSG | ||||||||||||||||||
| Draft Business Plan approved by LBTH | ||||||||||||||||||
| Business Plan approved by HARCA | ||||||||||||||||||
| LSG to vote on whether to approve Draft Offer | ||||||||||||||||||
| Draft Offer approved by LBTH | ||||||||||||||||||
| Draft Offer approved by OPDM | ||||||||||||||||||
| Draft Offer approved by HARCA Board | ||||||||||||||||||
| Stage 1 Notice - Draft Offer sent to Residents | ||||||||||||||||||
| Stage 2 Notice - Final Offer sent to Residents | ||||||||||||||||||
| B A L L O T | ||||||||||||||||||
| Legal Process of Transfer | ||||||||||||||||||
| (Work Begins) | ||||||||||||||||||