| No. | Item | Action | Current Status | Completion Date |
| 1 | Tree planting schedule will be prepared for next Tec Sub | BG | Environmental proposals indicate location of new trees. Species to be agreed with BG & PH following tech sub meeting | 14 November 2006 |
| 2. | Baily Garner will carry out a survey and include methods to protect trees as part of the environmental strategy. | PH | Tree survey will be completed by PH by end of Nov. This will include listing species of trees, dimension and numbering trees | 14 November 2006 |
| 3. | Schedule of works programme, once agreed by successful contractor will be circulated to all tenants through a newsletter. | LR | Newsletter to be circulated Jan 07 | End January 2007 |
| 4. | It was asked what type of windows will be installed in conservation area, | BG | Baily Garner will bring this to tech sub meeting in 2007 | September 2007 |
| 5. | There was a request to view the proposed designs to external areas; Baily Garner will provide this at next sub Tec meeting. | BG | To be presented 19th Sept 06 | 14 November 2007 |
| 6. | Access to off road parking on Ricardo Street to Elgin House is restricted at school drop off time, it will be explored if traffic wardens can patrol. | LR | LBTH advised no traffic warden enforcement would take place. No enforcement control currently on estate. Once enforcement is in place hatching will be carried out. | Ongoing |
| 7. | Recycling strategy to be made available by the end of September 2006. | BG/PH | Meeting held with LBTH . LBTH moving away from door step collection would like to have central locations for collections. Do not have resources to collect recycling from URSs. LBTH to forward PH information on recycling (awaited). BG to look at storage locations | Next Tech Sub Meeting |
| 8. | Harca would re-present options for compound sites once contractors have been appointed. | LR | To be presented Feb 07 | End February 2007 |
| 9. | Query on Final Transfer Report Does the £19,000 per annum increase? | RH | The £19k covers electricity and cleaning costs. The cleaning cost could go up if price of cleaning does. | No further Action required |
| 10. | What are the details of the grant for the canopy? In particular, can Harca change the canopy and, if there would be a cost involved, what would it be? | RH | The canopy is not owned by PH but we are obliged to maintain it. Currently 1 dangerous panel and 16 broken PH awaiting quotation. No works can be done in the market area without the consent of English Partnership as there is a covenant which prohibits no building, demolition etc within the boundary of the market because it's a Festival of Britain area. | No further action required |
| 11. | CCTV Plan: Harca did not provide a date for the plan to be delivered, although it was stated in the previous meeting that they would do so. It was emphasised that "plan" means detailed proposals of what will be done when rather than just a drawing. | BG | CCTV plan will be worked on once door entry and environmental strategies have been approved by tech sub | End February 2006 | 12. | Trees for Cities - 20 trees to be planted to improve south lansbury streetscape | TfC | March 2007 | 13. | Maidstone House - Closed off walkway, what are the plans for this area? | BG |
| Baily Garner Bradley Brown Fintan Tynan Lorraine Roach Lynda McShane Rob Hannabuss Tara Major Tracey Fletcher | BG - Architects/Master Planners BB - Estate Services Co-ordinator FT - Resident Empowerment Co-ordinator LR - Project Manager Technical Resources LM - Repairs Team Manager RH - Head of Regeneration TM - Neighbourhood Officer TF - Neighbourhood Director |