Log of Actions from Lansbury South Tec Sub Aug/Sept 06

Technical Sub Group Matters

No. Item Action Current Status Completion Date
1 Tree planting schedule will be prepared for next Tec Sub BG Environmental proposals indicate location of new trees. Species to be agreed with BG & PH following tech sub meeting 14 November 2006
2. Baily Garner will carry out a survey and include methods to protect trees as part of the environmental strategy. PH Tree survey will be completed by PH by end of Nov. This will include listing species of trees, dimension and numbering trees 14 November 2006
3. Schedule of works programme, once agreed by successful contractor will be circulated to all tenants through a newsletter. LR Newsletter to be circulated Jan 07 End January 2007
4. It was asked what type of windows will be installed in conservation area, BG Baily Garner will bring this to tech sub meeting in 2007 September 2007
5. There was a request to view the proposed designs to external areas; Baily Garner will provide this at next sub Tec meeting. BG To be presented 19th Sept 06 14 November 2007
6. Access to off road parking on Ricardo Street to Elgin House is restricted at school drop off time, it will be explored if traffic wardens can patrol. LR LBTH advised no traffic warden enforcement would take place. No enforcement control currently on estate. Once enforcement is in place hatching will be carried out. Ongoing
7. Recycling strategy to be made available by the end of September 2006. BG/PH Meeting held with LBTH . LBTH moving away from door step collection would like to have central locations for collections. Do not have resources to collect recycling from URSs. LBTH to forward PH information on recycling (awaited). BG to look at storage locations Next Tech Sub Meeting
8. Harca would re-present options for compound sites once contractors have been appointed. LR To be presented Feb 07 End February 2007
9. Query on Final Transfer Report Does the £19,000 per annum increase? RH The £19k covers electricity and cleaning costs. The cleaning cost could go up if price of cleaning does. No further Action required
10. What are the details of the grant for the canopy? In particular, can Harca change the canopy and, if there would be a cost involved, what would it be? RH The canopy is not owned by PH but we are obliged to maintain it. Currently 1 dangerous panel and 16 broken PH awaiting quotation. No works can be done in the market area without the consent of English Partnership as there is a covenant which prohibits no building, demolition etc within the boundary of the market because it's a Festival of Britain area. No further action required
11. CCTV Plan: Harca did not provide a date for the plan to be delivered, although it was stated in the previous meeting that they would do so. It was emphasised that "plan" means detailed proposals of what will be done when rather than just a drawing. BG CCTV plan will be worked on once door entry and environmental strategies have been approved by tech sub End February 2006
12. Trees for Cities - 20 trees to be planted to improve south lansbury streetscape TfC   March 2007
13. Maidstone House - Closed off walkway, what are the plans for this area? BG    

Officers Initials & Title:

Baily Garner
Bradley Brown
Fintan Tynan
Lorraine Roach
Lynda McShane
Rob Hannabuss
Tara Major
Tracey Fletcher
BG - Architects/Master Planners
BB - Estate Services Co-ordinator
FT - Resident Empowerment Co-ordinator
LR - Project Manager Technical Resources
LM - Repairs Team Manager
RH - Head of Regeneration
TM - Neighbourhood Officer
TF - Neighbourhood Director